York Civil have awarded the Queensbury Pump Station project to ICE, this is the 1st Project to be delivered under SA Waters new PMP (Project Management Panel). This project was won in a highly competitive environment due to the slowdown in projects across SA. ICE has delivered the majority of the larger capital projects for SA Water over the past 3 years, this experience has provided us with an intimate knowledge of the technical requirements that SA Water requires and thus has allowed us to develop internal systems and procedures to provide efficiencies when delivering these type of projects. This project will be delivered by ICE in parallel with the Happy Valley Chlorine Dosing project with a joint E&I project value of in excess of $1.5m and employing approximately 13 local electricians.